All trains
33660
Habra - Sealdah Local
Timeline not available
Select a run date above to load a timeline.
Delay along the route
Run history
About train 33660 — Habra - Sealdah Local
- Route
- Habra (HB) → Sealdah (SDAH)
- Distance
- 44 km
- Duration
- 1h 17m
- Halts
- 15
- Punctuality
- Habra - Sealdah Local arrived on time on 46% of its last 93 runs (averaging 19 min late). Delays build up most around Bidhan Nagar Road.
- Latest run
- On its latest recorded run (Sun, 26 Jul, 2026), it was running 23 min late at Narkeldanga Coaching Yard.
Schedule at a glance
- Habra HB14:58 / 14:580 km
- Ashok Nagar Road ASKR15:02 / 15:033 km
- Guma GUMA15:06 / 15:077 km
- Bira BIRA15:10 / 15:1110 km
- Dattapukur DTK15:15 / 15:1614 km
- Bamangachhi BMG15:19 / 15:2018 km
- Barasat Junction BT15:31 / 15:3222 km
- Hridaypur HHR15:34 / 15:3524 km
- Madhyamgram MMG15:37 / 15:3826 km
- New Barrackpore NBE15:40 / 15:4128 km
- Bisharpara Kodaliya BRPK15:43 / 15:4429 km
- Birati BBT15:46 / 15:4731 km
- Durganagar DGNR15:49 / 15:5032 km
- Dum Dum Cantt. DDC15:52 / 15:5334 km
- Dum Dum Junction DDJ15:58 / 15:5937 km
- Bidhan Nagar Road BNXR16:02 / 16:0340 km
- Kankurgachhi Road Cabin KGK16:08 / 16:0842 km
- Narkeldanga Coaching Yard NKG16:11 / 16:1143 km
- Sealdah SDAH16:15 / 16:1544 km